[ARCHIVED] Downtown Streetscape - Construction Update 08/03/2017

Construction

During week of July 31, the general contractor installed planter boxes and stamped concrete sidewalk on the north side of Main St. The underground contractor finished the water service transfers as well as connection to the new watermain at Main St and Roosevelt Ave.  


Weather permitting, week of August 7,  the general contractor is scheduled to perform removals on the south side of Main St while the underground contractor will begin the sanitary and storm improvements at the intersection of Addison/Roosevelt intersection. The intersection will be closed during work hours while this work is being performed. See attached map.


Nicor’s contractor NPL worked on installation of the new main this week but ran into conflicts with AT&T fiber optic. This fiber optic needs to be relocated which will delay finishing Nicor’s work by 2-3 weeks. They will be offsite until AT&T has relocated the fiber so Nicor can come back and abandon the old main. AT&T is scheduled to perform its work the week of Aug 7, 2017.


View More Construction Updates

Roosevelt/Addison Work Zone Map...
Facebook Twitter Email

Other News in Bensenville News

SOV_NF_TH

2026 State of the Village

Posted on: January 15, 2026
Valentines Bazaar_TH

Valentine's Day Bazaar

Posted on: January 15, 2026
Events_TH

Bensenville Special Events 2026

Posted on: January 14, 2026
Adjusted_TH

2026 Saturdays Hours

Posted on: January 1, 2026
CivicReady_NewsflashTH

CivicReady Alerts & Notifications

Posted on: November 29, 2025
TreeTrimmin_TH

ComEd Vegetation Management

Posted on: December 8, 2025
Warming_Newsflash_ 400x250

Warming Centers

Posted on: November 27, 2025
AquaHawk

Bensenville AquaHawk Alerting System

Posted on: April 3, 2022